St. Charles Building Timeline

Parish releases timeline for building of St. Charles This week we’d like to share with you the proposed project timeline: Ø 1/1/17 Architect Firm Retained Ø 6/1/17 Marketing Firm Retained Ø 10/17/17 Conditional Use Permits—Process Completed Ø 2/6/18 Cost Estimates Completed Ø 3/1/18 Building Permits Submitted Ø 5/3/18 Obtain Building Permit Ø 5/4/18 Construction Begins Ø 11/4/19 Construction Complete! Visit www.stcharlesvisalia.com to learn…